Q: |
I am in the process of building a new home, when should I start thinking about audio and video. |
|
A: |
The best time to contat Homedia Solutions about your system needs is when you have a set of working drawings. Your floor plans and elevations of planned equipment locations are most critical for the initial design meeting. The installation of system wiring begins immediately after your electrician is done with the high voltage wiring and before insulation is installed in the walls. Before we will begin wiring any system we need to agree on a your custom design plan or package, order the materials for wiring it and schedule the work. The typical lead time for packaged systems is 10 to 14 days, custom designs may take longer. |
|
|
|
|
|
|
|
|
|
 |
|
|
|
|